Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Light Rail Project

Dáil Éireann Debate, Thursday - 19 July 2012

Thursday, 19 July 2012

Ceisteanna (801)

Dessie Ellis

Ceist:

810 Deputy Dessie Ellis asked the Minister for Transport, Tourism and Sport the current spend on the Luas BXD project. [36085/12]

Amharc ar fhreagra

Freagraí scríofa

As Minister for Transport, Tourism and Sport I have responsibility for policy and overall funding in relation to public transport. Following the establishment of the National Transport Authority (NTA) in December 2009, the implementation and development of infrastructure projects in the Greater Dublin Area (GDA), such as LUAS BXD, comes under the remit of the NTA.

The allocation for BXD for 2012 is therefore a matter for the NTA having regard to the current state of progress as regards the project which still awaits planning approval. The spend to end 2011 as reported to me by the NTA was €11.7 million.

Barr
Roinn