Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 9 July 2013

Tuesday, 9 July 2013

Ceisteanna (230)

Patrick Nulty

Ceist:

230. Deputy Patrick Nulty asked the Minister for Education and Skills when construction of the extension to Castleknock community college, Dublin 15, will commence. [33404/13]

Amharc ar fhreagra

Freagraí scríofa

The major building project for Castleknock Community College is at an advanced stage of architectural planning, stage 2b. Further clarification on the stage 2(b) submission was recently received by the Department from the school authority and this is currently under review. Authorisation has been given to commence the pre-qualification process for contractors. On satisfactory completion of stage 2 (b) and assuming no issues arise, authorisation will be given to commence the tender process.

Question No. 231 answered with Question No. 214.
Barr
Roinn