Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Consultancy Contracts Data

Dáil Éireann Debate, Thursday - 3 July 2014

Thursday, 3 July 2014

Ceisteanna (142)

Barry Cowen

Ceist:

142. Deputy Barry Cowen asked the Minister for the Environment, Community and Local Government if he will provide in tabular form per annum all external consultant reports commissioned by his Department since March 2011; the costs per report; the company involved; the title of the report and its publication date. [28843/14]

Amharc ar fhreagra

Freagraí scríofa

The information requested is set out in the following table.

Year Commissioned

Consultant/Author etc.

Name/Description of Report/Review/Study

Date or Expected Date of Publication

Amount Spent Since March 2011

2011

Building Research Establishment Ltd

Retrofitting Code of Practice.

Published March 2014.

(1)€21,190

2011

Pyrite Panel

Report of the Pyrite Panel - Independent report to provide options for the Minister to deal with the pyrite problem.

Published July 2012.

€21,470

2011

Secretariat to the National Economic and Social Council of Ireland

Analysis on national climate policy.

Interim report released October 2012; final report released in February 2013.

Nil

2011

Mr. David Lovegrove

2011 Report of the Dormant Accounts Board.

Published July 2012.

€9,689

2011

Pembroke Communications

Advise on, and assist tendering process for, Tidy Towns sponsorship.

No formal report due for publication.

€4,560

2011

Barrow Archaeological Services

Archaeological reports on Met Éireann site at Valentia.

The report is not intended to be published as it is a technical report relating to a site on Valentia Island where Met Éireann are building an Air Monitoring Facility.

€1,210

2011

Malachy Walsh & Partners

EIS Screening Report for site at Valentia.

The report is not intended to be published as it is a technical report relating to a site on Valentia Island where Met Éireann are building an Air Monitoring Facility.

€6,336

2011

National Standards Authority of Ireland (NSAI)

Audit reports for ISO9001:2008 in 2011 and 2012.

Not intended for publication.

€6,699

2011

ARUP Consulting Engineers

Study in respect of provision of fire detection and alarms systems in dwellings.

Not intended for publication. It is a technical report, to inform work in the Department.

€29,935

2011

Murtagh & Partners

Review of Dublin Region Homelessness Services and Funding in 2011.

Published October 2011.

€27,800

2011

Housing & Sustainable Communities Ltd.

Toolkit for Local Authorities on regeneration.

Not intended for publication. This was a report intended to provide assistance to Local Authorities in drawing up proposals for the regeneration of their areas.

€12,300

2011

Dr. Eoin O'Sullivan, Trinity College Dublin

Review of the Homeless Strategy 2008-2013.

Published November 2012.

€6,000

2011

Indecon

Regulatory Impact Analysis of proposed regulations for household food waste.

Published June 2012.

€24,725

2011

Tobin Consulting Engineers

National Litter Pollution Monitoring System - 2011 Report.

Published April 2012.

€61,077

2011

Certification Europe Ltd

Compost Quality Assurance Scheme.

Published October 2012.

€139,142

2011

RPS Group

Provision of expertise concerning Strategic Environmental Assessment and Appropriate Assessment techniques for the evaluation and revision of Regional Waste Management Plans.

No formal document due for publication. The work comprises principally advice, guidance documents and technical expertise.

€45,223

2011

SKM Enviros

Irish Recycled Plastic Waste Arisings Study.

Published September 2011.

€37,566

2011

White Young Green

Annual Dust Impact Assessment Report (2011) at the Former Irish Steelworks Site, Haulbowline, Cobh, Co. Cork.

Published March 2012.

(2)see footnote

2011

Marine Institute

Marine Strategy Framework Directive - Initial Assessment.

The technical report was published on the Department's website in Q2 2013 and the summary report was published in Q4 2013.

(3)€1,475,006

2011

Price Waterhouse Coopers

Independent assessment on establishment of National Water Utility.

Irish Water - Phase 1 report and appendices published January 2012. Implementation Strategy published December 2012.

€179,584

2012

AECOM

Cost optimal study for non-domestic buildings.

Published March 2013.

€56,227

2012

Mr. David Lovegrove

2012 Report of the Dormant Accounts Board.

Published March 2013.

€1,120

2012

DKM Economic Consultants

Review of Part V of the Planning and Development Act 2000.

Published July 2013.

€39,690

2012

Indecon

Feasibility study on a Tenancy Deposit Protection Scheme.

Published November 2012.

(4)€42,706

2012

Version 1

Evaluation of ICT Disaster Recovery configuration and capability.

Not intended for publication.

€9,363

2012

Economic and Social Research Institute (ESRI)

Analysis of Property Tax Options - a report to the Interdepartmental Expert Group on Property Tax.

Published December 2012

€60,280

2012

Inter-Departmental Group

Design of a Local Property Tax – Report of the Inter-Departmental Group.

Published December 2012

Nil

2012

Flynn Furney Consultants Ltd

Environmental Management Services re: review of CEMP at Valentia Site (Method Statement)

The report is not intended to be published as it is a technical report relating to a site on Valentia Island where Met Éireann are building an Air Monitoring Facility.

€3,167

2012

Glas Ecology

Environment Management Plan (Breeding Chough and Peregrine Survey, Valentia Island, Co. Kerry).

The report is not intended to be published as it is a technical report relating to a site on Valentia Island where Met Éireann are building an Air Monitoring Facility.

€4,920

2012

Munster Archaeology

Report on archaeological investigation/survey of Met Éireann site at Valentia.

Preliminary report published February 2014. Final report expected shortly.

€47,289

2012

Mr. Hendrik W van der Kamp

Independent Evaluation of the Planning Review Report 2012.

Published January 2013.

€12,096

2012

Padraic Thornton Planning & Environmental Consultancy

Preparation of EIA Guidelines.

Published March 2013.

€7,200

2012

Mr. Seamus Woulfe SC

Review of the management by the Department of an application by Wicklow County Council for loan approval in respect of the compulsory purchase of land at Charlesland, Co. Wicklow - Phase 1.

Published March 2012.

€19,680

2012

Mr. Seamus Woulfe SC

Review of the compulsory acquisition of land by Wicklow County Council at Charlesland, Co. Wicklow - Phase 2.

Published April 2013.

€49,200

2012

Commission for the Economic Development of Rural Areas (CEDRA)

Commission for the Economic Development of Rural Areas report on how to support the economic development of rural Ireland.

Published April 2014.

(5)€19,049

2012

Housing and Sustainable Communities Agency

Review of leasing model.

The Report will be published following completion of the review process in the context of the development of a strategy for social housing later in 2014.

€1,937

2012

RPS Group

All Island Used Tyre Survey.

Published March 2013.

(6)€17,673

2012

RPS Group

Review of the Producer Responsibility Model in Ireland.

Four reports published in 2013 and remainder to be published early in Q3 2014

€211,458

2012

Tobin Consulting Engineers

National Litter Pollution Monitoring System - 2012 Report.

Published April 2013.

€58,271

2012

Fehilly Timoney & Company

Bulky Waste Reuse Best Practice - Feasibility Study.

Published July 2013.

€55,289

2013

Garrett Fennell Solicitor

Independent Review of the registration arrangements for Architects under the Building Control Act 2007.

Published on the Department's website.

Nil (report produced on a pro-bono basis)

2013

Economic and Social Research Institute (ESRI) & University College Cork (UCC)

Technical support on developing low carbon sector roadmaps for Ireland.

The project relates to technical support, with no formal document due for publication.

€107,552

2013

Economic and Social Research Institute (ESRI) & University College Cork (UCC)

Technical support for the purposes of advising Government on the proposed 2030 EU Framework for Climate and Energy Policies.

No formal document due for publication. The project relates to technical support.

€30,496

2013

AP Env Econ Limited

Ireland’s Environmental Data: Inventory, Assessment and Next Steps.

Published April 2014.

€35,178

2013

SLR Environmental Consulting (Ireland) Ltd

Wind Energy in Ireland: Building Community Engagement and Social Support.

To be published July 2014.

€50,451

2013

Indecon

Assessment of Potential Merits of New Initiative re Purchase of Local Authority Houses by Existing Tenants.

Not intended for publication.

Nil (report produced on a pro-bono basis)

2013

Userneeds

Usage survey on the Met Éireann website.

Not intended for publication - this was a report volunteered to Met Éireann by the survey company on a 'sample' basis.

Nil - provided as a 'free sample'

2013

KW Research & Associates

NTACC Research into why Travellers leave Traveller-specific accommodation.

Completed. Published on Department's website April 2014.

€9,921

2013

Housing and Sustainable Communities Agency

Business Process Design of the Housing Assistance Payment.

Not intended for publication at this time pending enactment of the Housing Bill 2013.

€54,938

2013

Housing and Sustainable Communities Agency

Review of CALF assessment process.

The Report will be published following completion of the review process in the context of the development of a strategy for social housing later in 2014.

€11,675

2013

Tobin Consulting Engineers

National Litter Pollution Monitoring System - 2013 Report.

Published June 2014.

€52,014

2013

Environmental Protection Agency (EPA)

Article 29(2) Report on

Progress on Implementation of the EC (Good Agriculture Practices for the Protection of Waters) Regulations 2010.

Published April 2014.

Nil

2013

RPS Group

Public consultation process on the Marine Strategy Framework Directive and producing a report.

Published November 2013.

€9,000

2013

Economic and Social Research Institute (ESRI)

Affordability aspects of the provision of water services in Ireland and subsequent analysis.

Published in May 2014 as Appendix 2 and Appendix 5 of the "Report of the Inter-Departmental Working Group on Affordability Measures".

€57,655

2013

Deloitte & Touche

Expert Assistance in the Local Government Shared Services Programme

The project relates to technical support, with no formal document due for publication.

€39,299

2014

Ricardo-AEA

NSMC Residential Solid Fuel Study

October 2014

(7)€40,000 (estimate)

2014

MacCabe, Durney Barnes

Independent Planning Review.

Expected to be published in September 2014.

€18,600

2014

Padraic Thornton Planning & Environmental Consultancy

Independent Review of Draft S31 Directions in Westmeath.

Published May 2014.

€5,000

2014

Tobin Consulting Engineers

National Litter Pollution Monitoring System - 2014 Report.

Expected to be published May 2015.

€52,013 (estimate)

(1) The contract is in conjunction with the Sustainable Energy Authority of Ireland. Total cost of the study is €169,302 (inclusive of VAT). My Department's contribution is €21,190 (inclusive of VAT) with the balance being met by the Sustainable Energy Authority of Ireland (i.e. €148,112 inclusive of VAT).

(2) My Department previously provided funding to Cork County Council to support the production of an annual Dust Impact Assessment Report at the former Irish Steel site at Haulbowline Island. Following a Government Decision in June 2011, the Department of Agriculture, Food and the Marine assumed the lead role in relation to the remedial works necessary to be undertaken on the site. Accordingly, funding provided to Cork County Council for the annual Dust Impact Assessment Report 2011 and subsequent years is a matter for the Department of Agriculture, Food and the Marine.

(3) This report arises from a broader process connected with Ireland’s obligation to implement the EU Marine Strategy Framework Directive. The work primarily consists of a determination of the status of Ireland’s marine waters and the measures necessary to achieve, or maintain, the required status by 2020. The preparation of a draft Initial Assessment (under Art. 8 of the MSFD) including proposals for Good Environmental Status (Art. 9) and for draft Environmental Targets (Art.10)

- Creation of an Atlas of the Irish Marine Environment

- Development of an index of environmental and associated indicators

- Preparation of a summary report for use in public consultation (Art. 19)

- Development of a streamlined national reporting system

(4) This report was co-funded by my Department and the Private Residential Tenancies Board. The cost to my Department of €42,706 represents 50% of the total cost.

(5) This report has been co-funded by my Department, Teagasc and the Western Development Commission. The cost to my Department of €19,049 represents 40% of the overall expenditure.

(6) Survey jointly commissioned and funded by Department of the Environment in Northern Ireland and my Department.

(7) This report has been commissioned by my Department under the auspices of the North South Ministerial Council and in conjunction with the Department of the Environment for Northern Ireland. The cost is being evenly split and the final charge to my Department is estimated at €40,000.

Barr
Roinn