191. Deputy Terence Flanagan asked the Minister for Public Expenditure and Reform the position regarding an Office of Public Works-owned premises (details supplied); and if he will make a statement on the matter. [47224/14]

Amharc ar fhreagra

Freagraí scríofa

The planning process for relocation of the Dublin City Mortuary and the State Pathologist into refurbished premises at the former Whitehall Garda Station Dublin 9 has been completed.

Tenders for the main works will be sought in early 2015 with appointment of the Contractor expected by end of Q1 2015. The works are programmed to take 9 months to complete with handover expected towards the end of 2015.