The Fishery Harbour and Coastal Infrastructure Capital Development Programme, which my Department administers on an annual basis, provides funding for capital works at the six Fishery Harbour Centres including Howth. A total of €1.18 million was approved for works at Howth Fishery Harbour Centre under the 2014 Fishery Harbour and Coastal Infrastructure Development Programme. The following table provides a breakdown of the approved projects in 2014:
Approved Funding 2014
|
Project
€
|
Design & Planning for Pontoons between Middle & West Pier
|
100,000
|
Syncrolift Platform Painting & Repairs
|
80,000
|
Upgrading of Navigational Lights & Markers
|
20,000
|
East Pier Repairs
|
150,000
|
Upgrading of Electrical System (Phase 2)
|
500,000
|
Disability Access
|
20,000
|
Safety & Maintenance
|
310,000
|
I have allocated €11.5 million in voted funds for the 2015 Fishery Harbour and Coastal Infrastructure Capital Development Programme. Decisions on the projects for inclusion under this programme will be based on an evaluation of the priorities across the six Fishery Harbour Centres taking due account of the overall funds available.