Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Flood Relief Schemes Status

Dáil Éireann Debate, Tuesday - 9 June 2015

Tuesday, 9 June 2015

Ceisteanna (402)

Seán Kyne

Ceist:

402. Deputy Seán Kyne asked the Minister for Public Expenditure and Reform if he will report on the status of a works scheme (details supplied) in County Galway, in view of the delay to the project; and when it is envisaged works will commence. [22460/15]

Amharc ar fhreagra

Freagraí scríofa

The Office of Public Works (OPW) has submitted the proposals for the Clare River (Claregalway) scheme for statutory approval by the Minister for Public Expenditure and Reform, as required by the Arterial Drainage Acts.

A report commissioned by the Department of Public Expenditure and Reform on a required independent evaluation of the Environmental Impact Statement prepared for the Scheme by the OPW is under consideration by that Department. A decision on the approval of the Scheme is expected shortly.

It is hoped that construction works could commence this Summer, with completion in 2017.

I wish to re-affirm that the OPW remains committed to carrying out the scheme, subject to the Minister's sanction, and has provided for its cost in its multi-annual capital expenditure profiles to 2017.

Barr
Roinn