The school building project referred to by the Deputy is on the current 5 year construction programme announced in 2012. It is listed on the programme to proceed to tender and construction in 2015/16.
The project is at an early stage of Architectural Planning. The Pre Stage 1 meeting, was held in February 2015, and the Design Team and school authority were authorised to progress to Stage 2A, which is the developed sketch design stage. Upon successful completion of stage 2A and subject to no issues arising, this project will then be authorised to proceed to Stage 2B - Detailed Design Stage, which includes applications for Planning Permission, Fire Safety Certification, Disability Access Certification and the preparation of tender documents.