Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 30 June 2015

Tuesday, 30 June 2015

Ceisteanna (540)

Patrick O'Donovan

Ceist:

540. Deputy Patrick O'Donovan asked the Minister for Education and Skills when refurbishment and extension work will take place at a college (details supplied) in Dublin 16; the duration of such works; and if she will make a statement on the matter. [26167/15]

Amharc ar fhreagra

Freagraí scríofa

The project referred to by the Deputy is at an advanced stage of the Tender Process and subject to no issues arising is expected to commence on site by the end of the summer. Once the project commences on site the construction programme set by the design team envisages that it will take approximately twenty nine months to complete the full suite of accommodation and refurbishment.

Question No. 541 answered with Question No. 500.
Question No. 542 answered with Question No. 499.