Light Rail Projects Status

Dáil Éireann Debate, Tuesday - 14 July 2015

Tuesday, 14 July 2015

Ceisteanna (939, 940)

Olivia Mitchell

Ceist:

939. Deputy Olivia Mitchell asked the Minister for Transport, Tourism and Sport if the Luas cross-city utilities diversion works are on schedule to finish in September 2015 as indicated on the Luas cross-city website. [28935/15]

Amharc ar fhreagra

Olivia Mitchell

Ceist:

940. Deputy Olivia Mitchell asked the Minister for Transport, Tourism and Sport if he will provide an update on the Luas cross-city main infrastructure works, which according to the Luas cross-city website commenced in March 2015. [28936/15]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 939 and 940 together.

The National Transport Authority (NTA) has responsibility for the implementation and development of infrastructure projects in the Greater Dublin Area, including the Luas Cross City project.

I understand from the NTA that the utility works are approximately 90% complete and are on schedule for completion in September 2015.

I have referred the Deputy's question to the NTA for an update on the main infrastructure works. Please advise my private office if you don't receive a reply within 10 working days.