Hospitals Building Programme

Dáil Éireann Debate, Tuesday - 12 July 2016

Tuesday, 12 July 2016

Ceisteanna (95)

Lisa Chambers

Ceist:

95. Deputy Lisa Chambers asked the Minister for Health the status of the construction works at the Sacred Heart Hospital in Castlebar, County Mayo; and the expected completion date. [20980/16]

Amharc ar fhreagra

Freagraí scríofa

The 74 bed community nursing home extension and all associated works at the Sacred Heart Hospital in Castlebar is currently at construction stage.  Works commenced on site on the 27th June 2016 and are estimated to take 15 months to complete. Commissioning and equipping of the new facility will follow and on this basis the facility is expected to be operational in late 2017.