Broadband Service Provision

Dáil Éireann Debate, Tuesday - 18 October 2016

Tuesday, 18 October 2016

Ceisteanna (618)

David Cullinane

Ceist:

618. Deputy David Cullinane asked the Minister for Communications, Climate Action and Environment the status of the rolling out of fibre broadband along the L2026 from Droichead Bhaile an tSléibhe to the junction with the N25 in Waterford; and if he will make a statement on the matter. [30814/16]

Amharc ar fhreagra

Freagraí scríofa

The National Broadband Plan (NBP) aims to deliver high speed services to every city, town, village and individual premises in Ireland. The Programme for Government commits to the delivery of the NBP as a matter of priority.  This is being achieved through private investment by commercial telecommunications companies and through a State intervention in areas where commercial investment is not forthcoming. The formal procurement process for the State Intervention commenced in December 2015.

The procurement process aims to identify an entity or entities to build, roll-out, operate and deliver high speed broadband of at least 30 Mbps download and 6 Mbps upload speeds to all premises within the intervention area.  Last week, I announced that the three bidders in the procurement process have indicated that they are proposing a predominantly fibre-to-the-home solution for rural Ireland under the National Broadband Plan intervention.  Householders and businesses may potentially get speeds not just of 30Mbps but up to 1Gbps with businesses potentially availing of symmetrical upload and download speeds. This is a solution that will endure for 25 years and beyond and put Ireland to the forefront internationally in terms of connectivity. 

The High Speed Broadband Map, which is available at www.broadband.gov.ie shows the extent of the State Intervention area:

- The areas marked BLUE represent those areas where commercial providers are either currently delivering or have previously indicated plans to deliver high speed broadband services. 

- The areas marked AMBER on the High Speed Broadband Map represent the target areas for the State Intervention which are the subject of the current procurement process.

Individuals can check whether their premises is in a BLUE or an AMBER area by scrolling through the map online or entering their Eircode. The Department also has a dedicated mailbox and anyone with a query in relation to the Map should email the Department, quoting their Eircode, to broadband@dcenr.gov.ie.   

Over 17,800 premises in County Waterford are within the AMBER area and will be covered by the State Intervention, including the area between Droichead Bhaile an tSléibhe to the junction with the N25 in Waterford.  This area will therefore be included in the procurement process.

The Department is now in a formal procurement process to select a company or companies who will roll-out a new high speed broadband network to the over 750,000 premises in Ireland, covering 100,000km of road network and 96% of the land area of Ireland.

In parallel, my Department continues to liaise closely with industry and relevant other Departments and agencies to assist in the commercial deployment of telecommunications networks. The commercial telecommunications sector has invested over €2bn in upgrading and modernising networks which support the provision of high speed broadband and mobile telecoms services. These investments will further improve the coverage and quality of broadband and mobile voice and data services throughout the country.

In line with commitments in the Programme for Government I established a Mobile Phone and Broadband Taskforce with my colleague Minister Humphreys in July 2016. The Taskforce will recommend practical actions that can be taken in the short-term to improve mobile phone and broadband access in Ireland, working with Government Departments, Local Authorities, ComReg, State Agencies, the telecoms industry and other key stakeholders. The work of the task force will also assist Local Authorities in preparing for the roll-out of the new NBP network once contract(s) are in place. I expect that Minister Humphreys and I will bring proposals to Government by the end of 2016, on foot of the Taskforce's report.

Barr