North-South Interconnector

Dáil Éireann Debate, Wednesday - 26 October 2016

Wednesday, 26 October 2016

Ceisteanna (44)

Timmy Dooley

Ceist:

44. Deputy Timmy Dooley asked the Minister for Communications, Climate Action and Environment his views on the undergrounding of the National Small Industries Corporation using high-voltage direct current technology; and if he will make a statement on the matter. [32067/16]

Amharc ar fhreagra

Freagraí scríofa

I believe the question refers to the North-South 400kV Interconnector project.  

EirGrid is the designated Transmission System Operator and its role includes the operation, maintenance and development of the electricity transmission network in Ireland. As detailed in the government Policy Statement on the Strategic Importance of Transmission and Other Energy Infrastructure, the Government does not seek to direct EirGrid in the development of energy infrastructure to particular sites or routes or technologies.  

EirGrid made a formal application for the North-South 400kV Interconnector project to An Bord Pleanála on 9 June 2015. This is the subject matter of a statutory independent planning process currently before An Bord Pleanála. One part of the process was an oral hearing that concluded 23 May 2016. As the planning process is still ongoing it would not be appropriate for me to comment further.  

The case is due to be decided by 21 December 2016, according to the An Bord Pleanála website.