The information requested by the deputy is set out in the following table. I have extended the deadline for the completion of the carbon navigators by one month to 30 November to enable all participants to complete the navigator in order that payment can issue to them in December, subject to all other requirements having been met.
County
|
Carbon Navigators Completed
|
Carlow
|
190
|
Cavan
|
810
|
Clare
|
1238
|
Cork
|
1393
|
Donegal
|
1090
|
Dublin
|
17
|
Galway
|
2018
|
Kerry
|
926
|
Kildare
|
243
|
Kilkenny
|
428
|
Laois
|
483
|
Leitrim
|
761
|
Limerick
|
509
|
Longford
|
439
|
Louth
|
186
|
Mayo
|
1679
|
Meath
|
371
|
Monaghan
|
650
|
Offaly
|
430
|
Roscommon
|
1155
|
Sligo
|
795
|
Tipperary
|
683
|
Waterford
|
316
|
Westmeath
|
547
|
Wexford
|
459
|
Wicklow
|
318
|
Total
|
18134
|