Departmental Funding

Dáil Éireann Debate, Tuesday - 17 January 2017

Tuesday, 17 January 2017

Ceisteanna (731)

Dara Calleary

Ceist:

731. Deputy Dara Calleary asked the Minister for Public Expenditure and Reform if he will outline all funding announcements made by him or by his Department for projects in County Mayo since January 2015, in tabular form; the details of each project; the status of the project at 31 December 2016; the amount of funding drawn down at 31 December 2016; and the reason for the delay in the project or funding draw down. [1064/17]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy will be aware, the Government's Capital Plan was announced on 29 September, 2015 and outlined exchequer capital spending of €27 billion over the next six years. In the 2016 Summer Economic Statement, the Government committed to additional capital investment of €5.14 billion over the period of the plan.

Individual Ministers will be able to advise on the range of projects in County Mayo that are being funded under the Capital Plan by the relevant line Departments.

In relation to my Department, the Office of Public Works (OPW) has provided funding for flood risk projects in County Mayo since January 2015 and details of these projects are set out in the following tables:

Minor Flood Mitigation Works and Coastal Protection Scheme     

Local Authority

Project Location

Project Details

Approved Funding

Date of Approval

Status of Project

Funding Drawn-down

Mayo County Council

Barnagreggaun/             Mossbrook, Balla

Clean drains, install pipe & construct banking alongside road

€5,760

21/09/15

Completed

€5,184

 

Additional storm damage funding

Additional once off funding allocation to enable local authority to address outstanding storm damage repairs to public coastal protection infrastructure arising from the second period of severe weather during the Winter 2013/2014 storms

€6,000

08/10/15

Completed

€6,000

 

Total (2015)

 

€11,760

 

 

€11,184

Mayo County Council

Salmon Leap Cottage, Belclare

Divert flood waters away from house back into main channel

€9,000

14/03/16

 

€0

 

 

Crossmolina Car Park

 

 

To remove existing railing, construct wall & flood barrier & associated works

€95,220

11/08/16

Ongoing

€47,708

 

 

Crossmolina Walkway

 

 

 

To remove existing shrubbery, construct walls, supply & install flood gate & associated works

€64,350

11/08/16

Ongoing

€40,173

 

 

Crossmolina, Chapel Street

 

 

To repoint/repair existing stone wall

€29,700

 

11/08/16

Ongoing

€20,792

 

 

Copper Beach, Straide

 

Raise embankment at site - 35m embankment 5600 high with slopes 1:1

€5,490

07/11/16

 

€0

 

 

Seasonmaster, Straide

 

175m long raised embankment at site perimeter

Raise road surface above adjacent watercourse

€28,575

07/11/16

 

€0

 

Total (2016)

 

€232,335

 

 

€108,673

The Office of Public Works is not involved in the day-to-day administration and management of the Minor Works projects. The commencement and progression of the approved projects is a matter for the local authority.

Crossmolina Flood Gates Pilot Project

Local Authority

Project Location

Project Details

Approved Funding

Date of Approval

Status of Project

Funding Drawn-down

Mayo County Council

Crossmolina

Survey and assess suitability of properties at risk of flooding for installation of flood gates; recommend and install flood gates in suitable properties

 

 

No specific funding amount approved but Office of Public Works has committed to fund the cost of the pilot project

Jan 2016

Ongoing. House surveys completed. Work on installation of flood gates due to commence in week beginning 9/01/17

€0

 

Barr