National Children's Hospital Expenditure

Dáil Éireann Debate, Thursday - 19 January 2017

Thursday, 19 January 2017

Ceisteanna (218, 220, 221)

Jack Chambers

Ceist:

218. Deputy Jack Chambers asked the Minister for Health the detail of all sunk costs associated with the construction of the new national children's hospital at the St. James’s Hospital site, in tabular form; and if he will make a statement on the matter. [2381/17]

Amharc ar fhreagra

Jack Chambers

Ceist:

220. Deputy Jack Chambers asked the Minister for Health the costs to date spent on consultants or experts associated with the construction of the national children's hospital at the St. James's Hospital site, in tabular form; and if he will make a statement on the matter. [2383/17]

Amharc ar fhreagra

Jack Chambers

Ceist:

221. Deputy Jack Chambers asked the Minister for Health projected costs yet to be paid to consultants or experts associated with the construction of the national children's hospital at the St. James's Hospital site, in tabular form; and if he will make a statement on the matter. [2384/17]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 218, 220 and 221 together.

The National Paediatric Hospital Development Board is the statutory body charged with delivery of the capital project. I have asked it to respond to you directly regarding costs to date and expected expenditure on consultants and experts.

Barr