Cross-Border Projects

Dáil Éireann Debate, Thursday - 9 February 2017

Thursday, 9 February 2017

Ceisteanna (163)

Brendan Smith

Ceist:

163. Deputy Brendan Smith asked the Minister for Arts, Heritage, Regional, Rural and Gaeltacht Affairs when the restoration of the Ulster Canal will proceed to the next stage; the funding allocated for this project in 2017; and if she will make a statement on the matter. [6511/17]

Amharc ar fhreagra

Freagraí scríofa

Government approval to restore a 2.5km stretch of the Ulster Canal from the Shannon-Erne Waterway to the International Scout Centre at Castle Saunderson, Co. Cavan was granted on 24 February 2015. The project, which comprises three work phases, is being undertaken by Waterways Ireland.

Waterways Ireland is in the final stages of the tender assessment process for Phase 3 of the Ulster Canal works which will extend navigation to Castlesaunderson, Co. Cavan.

It is expected that the contract will be awarded by the end of February 2017. It is anticipated that a contractor will be on site towards the end of April 2017.

A budget of €1.8m has been allocated to this project for 2017.