Dáil Éireann Debate, Thursday - 18 May 2017

Thursday, 18 May 2017

Ceisteanna (156)

John Curran

Ceist:

156. Deputy John Curran asked the Minister for Housing, Planning, Community and Local Government the scheme of rapid build housing which will be completed next and ready for occupation; when this scheme will be complete; the number of units of accommodation which will be provided; and if he will make a statement on the matter. [23892/17]

Amharc ar fhreagra

Freagraí scríofa

My Department is working closely with all local authorities in relation to increasing and accelerating the delivery of a range of social housing programmes and supports, including rapid build/delivery homes. At the end of 2016, a total of 350 rapid build homes were advancing through various stages of delivery, including construction, with 22 such homes being delivered and occupied in 2016. Over 500 rapid build homes are now advancing and work is underway at advancing a further 500 rapid build homes in 2017, with another 500 units to be delivered in 2018.

In relation to the 350 rapid build homes that were advancing at the end of 2016, the following are the 11 projects concerned:

Projects

Units of accommodation

George’s Place, Dun Laoghaire                           

12 homes

St. Aidan’s, Brookfield

71 homes

Poppintree, Ballymun

22 homes (completed)

Cherry Orchard, Ballyfermot                             

24 homes

Mourne Road, Drimnagh

30 homes

St. Helena’s, Finglas                                    

39 homes

Belcamp, Dublin, 17

38 homes

Cherry Orchard, Ballyfermot

52 homes

Woodbank, Rathvilly                                        

18 homes

Wellview, Mulhuddart                                         

20 homes

Pinewood, Balbriggan 

24 homes

Of these projects, the following are currently on site and are due for completion this year:

Projects

Units of accommodation

Completion date

St. Helena’s, Finglas

39 homes

June

Mourne Road, Drimnagh

30 homes

July

Cherry Orchard

24 homes

July

Belcamp, Dublin 17                                         

38 homes

September

Wellview, Mulhuddart                                      

20 homes

November

It should be noted that Dublin City Council is in negotiation with the contractors in order to accelerate delivery and ensure a phased hand-over of these rapid build homes. The next phase of 70 rapid build homes will commence in Dublin City with the award of contracts in June 2017, with work then commencing on site. 

A further 5 schemes, which will deliver 177 units, were approved under the Rapid Delivery Programme in Quarter 1, 2017. They are:

Projects

Units of accommodation

Hansfield, Dublin 15                                            

36 homes

Avondale, Mulhuddart                                         

44 homes

Killininney, Firhouse                                           

24 homes

St. Cuthberts, Clondalkin

59 homes

Glenamuck/Rockville, Dun Laoghaire

14 homes

I expect further projects, particularly in the Greater Dublin Area, to be brought forward shortly.