Under my Department's social housing capital programme, there are over 500 rapid build homes advancing at present. Details in relation to the projects referred to in the Question are set out as follows.
Cherry Orchard, Ballyfermot
|
24 homes, scheduled for delivery July 2017
|
Mourne Road, Drimnagh
|
30 homes, scheduled for delivery July 2017
|
St. Helena’s, Finglas
|
39 homes, scheduled for delivery July 2017
|
Belcamp, Dublin,17
|
38 homes, scheduled for delivery September 2017
|
Wellview, Mulhuddart
|
20 homes, scheduled for delivery November 2017
|
Woodbank, Rathvilly
|
18 homes, scheduled for delivery end 2017/early2018
|
Cherry Orchard, Ballyfermot
|
52 homes, scheduled for delivery end 2017/early 2018
|
St. Aidan’s, Brookfield
|
71 homes, scheduled for end 2017/early 2018
|
Pinewood, Balbriggan
|
24 homes, scheduled for delivery end 2017/early2018
|
George’s Place, Dun Laoghaire
|
12 homes, scheduled for delivery in early 2018
|
My Department has recently asked all Local Authorities to review the social housing projects in their areas and in the interest of achieving earliest delivery, they have been requested to consider their suitability for Design and Build contracts under the Framework set up by the Office Of Government Procurement. They are being asked to consider, in particular, schemes which are amendable to early commencement, particularly in terms of their approved planning status.