The construction of the new Forensic Science Laboratory is being managed by the Office of Public Works (OPW) on behalf of my Department.
In the region of €1.33 million has been spent to date on a package of enabling works at the Backweston site.
I am pleased that significant financial provision has been made for the completion of the laboratory. However, the Deputy can appreciate that the cost of construction and fit-out will only be known once the tendering process is complete.
The submission date for tenders for the main construction works has recently been deferred as, owing to the complexity of the project and recent changes in international Forensic Laboratory Standards, it will be necessary to add further material to the tender documentation.
Forensic Science Ireland and the Project Design Team are currently examining the issues involved which relate primarily to laboratory interior finishes and mechanical and electrical adjustments. The relevant contractors have been apprised of the situation and the objective is to progress the tender competition as soon as possible.
There will be substantial construction work carried out over the next two years or so and I would expect the new laboratory to be ready in early 2021.