I propose to take Questions Nos. 67 to 69, inclusive, together.
I understand that the Deputy is referring to Parliamentary Question Nos. 128 and 129 of 19 April 2018.
I am informed by Revenue that there is a dedicated team which looks after applications for relief under the Employment and Investment Incentive (EII) and the Start-Up Relief for Entrepreneurs (SURE). There is currently 4 full time equivalent staff in this team.
In relation to the number of applications open for 0-3 months and for 3-6 months, owing to the way Revenue tracked correspondence it is not possible to provide this information for files dealt with prior to August 2017. As set out in my replies to Parliamentary Question Nos 128 and 129 of 19 April 2018, an open item may be the subject of ongoing correspondence with Revenue during that period. The length of time it is open refers to the length of time from when the application was made to when it is fully dealt with.
All files are dealt with in date order. However, where additional information is requested from a taxpayer they are given a 14 day window and if they reply within that window they remain at the top of the queue, rather than being returned to the end of the queue, as would happen if a strict date order approach was taken.
The following table sets out the age distribution of cases open at the end of each month:
Month
|
No. open items
|
Open 0-3 months
|
Open 3-6 months
|
Open 6+ months
|
August 2017
|
164
|
133
|
31
|
-
|
September 2017
|
186
|
165
|
21
|
-
|
October 2017
|
277
|
227
|
50
|
-
|
November 2017
|
189
|
152
|
37
|
-
|
December 2017
|
187
|
170
|
17
|
-
|
January 2018
|
189
|
83
|
103
|
3
|
February 2018
|
188
|
63
|
119
|
6
|
March 2018
|
180
|
75
|
96
|
9
|
There are two stages to the EII relief and both require an application at the appropriate time. Therefore the figures of outstanding cases constitute a combination of the original application for the main relief (30/40s) and the follow-on application (10/40s) relating to the increase in employment.
Of the open cases at the end of January, February and March 2018:
- 80% are EII1 applications (the initial 30/40 relief) and
- 20% are EII1As (the 10/40 relief which may be claimed after 4 years).
In each of the months, approximately 150 EII1 applications were outstanding and approximately 30 EII1As (these figures are approximate on a monthly basis as records are updated in batches).
The breakdown as regards cases in which additional information was required is as follows:
|
|
New Applications not yet reviewed*
|
Further information required and requested – no response received*
|
Further information required, requested and received*
|
EII
|
80% of open cases
|
40%
|
50%
|
10%
|
EII1A
|
20% of open cases
|
85%
|
8%
|
7%
|
* Expressed as a percentage of EII1 / EII1A claims as appropriate
There are also two stages in the working of each of these applications – an initial screening for completeness of application and the case-working of the application for certification. At both stages, further information may need to be requested, and during the casework stage specific queries emerge that require further correspondence.
Of the new applications screened to date, less than one percent are fully complete for processing. Revenue expects this to improve as applicants begin using the new detailed application form designed to address the problems evidenced in the application process.