Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Office of Public Works

Dáil Éireann Debate, Tuesday - 8 May 2018

Tuesday, 8 May 2018

Ceisteanna (139)

Joan Burton

Ceist:

139. Deputy Joan Burton asked the Minister for Public Expenditure and Reform the estimated revenue in respect of events (details supplied); the arrangements to be made to reimburse the Phoenix Park to undertake reinstatement works following large crowd events; and if he will make a statement on the matter. [20162/18]

Amharc ar fhreagra

Freagraí scríofa

The Bloom Garden event and the proposed Papal Mass are Government- supported events and thus a facility fee is not charged in either case.

With regard to the “Ed Sheeran” concerts, the fees charged are commercially sensitive but are in line with fees charged at other similar venues. As is normal practice for such events, OPW has sought a substantial bond from the event promoter to fund any reinstatement works which may be necessary following these concerts.