Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Housing Data

Dáil Éireann Debate, Tuesday - 19 June 2018

Tuesday, 19 June 2018

Ceisteanna (600)

Eoin Ó Broin

Ceist:

600. Deputy Eoin Ó Broin asked the Minister for Housing, Planning and Local Government the number of Part V units delivered in each local authority area in 2017, in tabular form; and the average cost of those units in each area. [26697/18]

Amharc ar fhreagra

Freagraí scríofa

The data requested is currently being compiled and will be provided to the Deputy in accordance with Standing Orders.

The following deferred reply was received under Standing Order 42A
The total social housing delivery output for 2017 included 522 Part V units and a breakdown of this delivery by Local Authority is published on my Department’s website at the following link: http://www.housing.gov.ie/sites/default/files/attachments/2fa5-pt-v-area-2014-2017_0.xlsx.
Of the 522 units, 81 were delivered under the Social Housing Capital Investment Programme (SHCIP); 12 units were delivered under the Capital Assistance Scheme (CAS); 163 units were delivered under the Capital Advance Leasing Facility (CALF); 142 units were delivered through Leasing and 124 units were delivered by Local Authorities but were not submitted for recoupment of funding from my Department.
The table provides a breakdown of Part V by Local Authority, across the delivery streams described above, with the relevant average costs of units funded  through my Department.
With regard to units delivered under the Capital Advance Leasing Facility the total unit cost and the CALF amount approved (which is the maximum capital amount payable by the Department) have been provided. It is important to note that CALF is a loan which is fully repayable by the Approved Housing Body at the end of the term of the agreement. The average Payment and Availability Agreement (P&A) cost is also included in the table.
With regard to units delivered under Leasing, the Department does not provide capital funding for these units and the average Payment and Availability (P&A) Agreement cost is provided in the table.

LA

Total Part V output 2017

SHCIP Part V output 2017

Average Cost of SHCIP part V unit €

CAS Part V output 2017

Average Cost of CAS Part V unit €

CALF Part V output 2017

Average total cost of CALF Part V unit €

Average CALF Approved for CALF Part V unit €

Average annual P&A cost for CALF Part V unit €

Leased Part V unit output 2017

Average annual P&A cost €

Non DHPLG funded Part V units output 2017

Carlow

10

10

184,395

0

0

Cavan

1

1

130,000

0

Clare

4

4

222,500

0

0

Cork City

0

0

0

0

Cork County

7

5

179,772

0

2

Donegal

0

0

0

0

Dublin City

56

1

240,434

0

-

55

DLR

137

0

8

266,476

15,057

20,021

124

14,210

5

Fingal

101

11

206,855

66

222,464

32,511

14,431

24

Galway

34

2

32

189,287

56,474

9,670

0

Galway City

0

0

137,512

0

0

Kerry

0

0

0

0

Kildare

24

8

181,240

0

16

Kilkenny

3

0

3

93,503

13,090

6,584

0

Laois

1

1

165,000

0

0

Leitrim

0

0

0

0

Limerick

9

9

169,215

0

0

Longford

0

0

0

0

Louth

1

0

0

1

Mayo

0

0

0

0

Meath

23

0

12

233,157

61,458

15,088

11

Monaghan

5

5

206,117

0

0

Offaly

0

0

0

0

Roscommon

0

0

0

0

Sligo

6

0

6

238157

0

0

South Dublin

80

10

220,434

6

200000

36

257,496

64,328

15,346

18

13,754

10

Tipperary

0

0

0

0

Waterford

13

13

178,383

0

0

Westmeath

0

0

0

0

Wexford

6

0

6

203,846

61,154

9,384

0

Wicklow

1

1

315,000

0

0

All LAs

522

81

12

163

142

124

Barr
Roinn