2051. Deputy Robert Troy asked the Minister for Communications, Climate Action and Environment his plans to provide fibre optic broadband facilities in the Ballinalack and Rathowen areas of County Westmeath. [33351/18]

Amharc ar fhreagra

Freagraí scríofa

I refer to the to Question No. 472 of 11 July 2018. The Government's National Broadband Plan (NBP) aims to ensure high speed broadband access (minimum 30 megabits per second) to all premises in Ireland, regardless of location.  The NBP has been a catalyst in encouraging investment by the telecoms sector. Today, almost 7 out of 10 of the 2.3 million premises in Ireland have access to high speed broadband. Since this Government came into office almost 400,000 additional premises have access to high speed broadband. By 2020, 9 out of 10 premises will have access to a high speed broadband connection. 

In April 2017 I published an updated High Speed Broadband Map which is available at www.broadband.gov.ie. This map shows the areas targeted by commercial operators to provide high speed broadband services and the areas that will be included in the State Intervention Area under the NBP.

In April 2017, I also signed a Commitment Agreement with eir in relation to its plans to provide high speed broadband to 300,000 premises in rural areas on a commercial basis. Information on eir's planned rural deployment is available at http://fibrerollout.ie.  A copy of the Commitment Agreement is available on my Department’s website www.dccae.gov.ie

The High Speed Broadband Map is colour coded and searchable by address/eircode:

- The AMBER areas represent the target areas for the proposed State led Intervention under the NBP and are the subject of an ongoing procurement process. 

- The BLUE represent those areas where commercial providers are either currently delivering or have plans to deliver high speed broadband services. 

- The LIGHT BLUE areas represent eir's commercial rural deployment plans to rollout high speed broadband to 300,000 premises by the end of this year as part of the Commitment Agreement with eir.

The number of premises that fall into each of these categories in the areas referred to in the Question is outlined in the below table. Individuals can enter their eircode into the map to find out into which category their premises falls into.

Area

Total

Premises in AMBER

Premises in BLUE

Premises in LIGHT BLUE

Ballinalack

76

 

 

100% (76)

Rathowen

103

7% (7)

91% (94)

2% (2)

My Department is in a formal procurement process to select a company who will roll-out a new high speed broadband network in the State intervention area. That procurement process is now in its final stages.

For those premises currently awaiting access to high speed broadband, practical initiatives will continue to be addressed through the work of the Mobile Phone and Broadband Taskforce to address obstacles and improve connectivity in respect of existing and future mobile phone and broadband services.

Under this Taskforce, engagement between telecommunications operators and local authorities through the Broadband Officers is continuing to strengthen.  These Broadband Officers are acting as single points of contact in local authorities for their communities.  The appointment of these officers is already reaping rewards in terms of ensuring a much greater degree of consistency in engagements with operators and clearing obstacles to developing infrastructure. The Department of Rural and Community Development maintain a list of Broadband Officers, a link to which is available on my Department's website at https://www.dccae.gov.ie/en-ie/communications/topics/Broadband/national-broadband-plan/Pages/NBP-Information-Leaflets.aspx.