I propose to take Questions Nos. 529 and 544 together.
While this project is being developed by an approved housing body (AHB), its approval is a matter for Limerick City and County Council, in line with the arrangements under the Capital Assistance Scheme. At the request of the Council, my Department issued initial project approval in February 2017 for this project, involving the construction of 10 units of accommodation. This approval was subject to the project being advanced to the satisfaction of the Council.
I understand that the Council is working with the AHB on the design of the scheme and, at this stage, my Department is awaiting more detailed project plans. I am keen to see this and other such projects brought forward with completed designs as soon as possible and, accordingly, all parties should work to agree a design approach at the earliest possible opportunity.