Dáil Éireann Debate, Tuesday - 2 October 2018

Tuesday, 2 October 2018

Ceisteanna (508)

Micheál Martin

Ceist:

508. Deputy Micheál Martin asked the Minister for Communications, Climate Action and Environment the location of each of the 14 publicly accessible compressed natural gas refilling stations that Gas Networks Ireland is delivering; and the timeline for delivery of each of these stations. [39592/18]

Amharc ar fhreagra

Freagraí scríofa

The delivery of 14 Compressed Natural Gas filling stations, as part of the Causeway Project, is an operational matter for Gas Networks Ireland.

I have been provided with an update on the current status these stations by Gas Networks Ireland which is set out in the table below.

Location

Status

Station 1

Dublin Port

The station is constructed and has been commissioned. Gas has been successfully dispensed. A licence Application has been submitted to the Commission for Regulation of Utilities. The station is scheduled to be operational later this year.

Station 2

Exit 8, Cashel

Planning permission has recently been granted and the station is scheduled to be operational in 2019.

Station 3

Kinsale Road, Cork

Planning permission has recently been submitted and the station is planned to be operational in 2019.

Station 4, 5, 6, 7

Louth, Limerick, Portlaoise and Tipperary (exact locations to be confirmed)

Construction is likely to take place in 2019.

Station 8-14

To be confirmed.

Negotiations in relation to locations are ongoing.