Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Garda Stations

Dáil Éireann Debate, Wednesday - 3 October 2018

Wednesday, 3 October 2018

Ceisteanna (121)

Niamh Smyth

Ceist:

121. Deputy Niamh Smyth asked the Minister for Public Expenditure and Reform the status of the construction works at the new Bailieborough Garda station; the completion date for same; and if he will make a statement on the matter. [40194/18]

Amharc ar fhreagra

Freagraí scríofa

A Planning Application for this development commenced on 31 August 2018, under Part 9 of the Planning and Development Regulations. The period of public consultation ended on 11 September 2018. It is expected that this process will be concluded shortly.

At this point in time it is not possible to give a definitive completion date for the construction of the new Station until i) the Planning process, ii) the required Public Procurement process and iii) Contract Award are complete.

Barr
Roinn