136. Deputy Clare Daly asked the Minister for Public Expenditure and Reform further to Parliamentary Question No. 86 of 17 October 2018, if he will quantify the relatively small number of projects the €500,000 limit has been exceeded. [44085/18]

Amharc ar fhreagra

Freagraí scríofa

The Measured Term Maintenance Contract which expired on 12th October 2018 set a single order limit at €500,000 exclusive of VAT.  

During this contract i.e. from 13th October 2014 to 12th October 2018 the number of projects that have exceeded the contract limit of €500,000 exclusive of VAT were as follows:

Projects, that have exceeded €500k exclusive of VAT and that commenced between 13/10/2014 and 12/10/2018

Number of Projects

2014

0

2015

3

2016

2

2017

0

2018

7