Schools Building Projects Data

Dáil Éireann Debate, Tuesday - 6 November 2018

Tuesday, 6 November 2018

Ceisteanna (356)

Brendan Ryan

Ceist:

356. Deputy Brendan Ryan asked the Minister for Education and Skills if tenders have now been invited for the construction of a new school (details supplied) from the short-list of candidates drawn up after the pre-qualification process; if so, the closing date for receipt of tenders; and if he will make a statement on the matter. [45731/18]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is at an advanced stage of architectural planning, Stage 2(b) – Detailed Design which includes the application for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents. All statutory approvals have been secured.

The outcome of the pre-qualification process has been notified to contractors who expressed interest in tendering for this project. Feedback and issues arising from same are currently being dealt with by the school and its Design Team. When this process has concluded the project will then be progressed to tender stage.

A tender stage normally takes between 7 and 8 months to complete.

Question No. 357 answered with Question No. 307.