Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

National Children's Hospital Expenditure

Dáil Éireann Debate, Tuesday - 19 February 2019

Tuesday, 19 February 2019

Ceisteanna (404)

Michael McGrath

Ceist:

404. Deputy Michael McGrath asked the Minister for Health the provision on construction tender inflation in the contract regarding the guaranteed maximum price of €1.433 billion for the construction of the national children's hospital; the agreed method of measuring construction tender inflation under the contract; the extra amount that must be paid for each 1% that construction tender inflation exceeds the agreed threshold of 4%; and if he will make a statement on the matter. [8153/19]

Amharc ar fhreagra

Freagraí scríofa

There are clearly defined procedures around the recovery of excessive tender inflation in relation to the build cost for this project. The Guaranteed Maximum Price (GMP) procurement process agreed with the contractors requires the contractors to take all risk for quantities following completion of the GMP process, and, as per the contract, limits their recovery of additional costs incurred by them to clearly defined scope changes and in excess of 4% inflation (as per the average of three published tender price indices) which may occur post July 2019. In relation to the extra amount that must be paid for each 1% that construction tender inflation exceeds the agreed threshold of 4%, I have asked the National Paediatric Hospital Development Board to reply to you directly.

The independent review underway into the cost escalation associated with the new children's hospital construction project, as part of its Terms of Reference, will comment on the major residual risks and the robustness/completeness of the current forecasts and, where possible, quantify those risks contractually excluded from the GMP/adjusted contract sum. This review is expected to be completed by the end of March 2019.

Questions Nos. 405 to 407, inclusive, answered with Question No. 403.
Barr
Roinn