Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 8 May 2019

Wednesday, 8 May 2019

Ceisteanna (317)

Jack Chambers

Ceist:

317. Deputy Jack Chambers asked the Minister for Education and Skills when a school (details supplied) will go under construction and completion; and if he will make a statement on the matter. [19166/19]

Amharc ar fhreagra

Freagraí scríofa

A building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.  The project has been authorised to proceed to tender. 

Subject to no issues arising, it is envisaged that construction will commence in the final quarter of 2019, with a construction period of approximately 24 months.