41. Deputy Joan Burton asked the Minister for Education and Skills the timeline for the delivery of a new permanent school building for schools (details supplied); when the new school building will open; and if he will make a statement on the matter. [19831/19]

Amharc ar fhreagra

Freagraí scríofa

A building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.  The project was recently approved to proceed to tender. 

Subject to no issues arising, it is envisaged that construction will commence in the final quarter of 2019, with a construction period of approximately 24 months.