Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 10 July 2019

Wednesday, 10 July 2019

Ceisteanna (175)

Brendan Ryan

Ceist:

175. Deputy Brendan Ryan asked the Minister for Education and Skills further to Parliamentary Question No. 172 of 14 May 2019, if there has been further progress on the site acquisition; if a design team will be put in place for the three projects; the estimated timetable for the completion of the education campus; and if he will make a statement on the matter. [30092/19]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy has been informed previously, agreement in principle has been reached with a landowner for the acquisition of a site at Donaghcumper, Celbridge. This site is proposed to facilitate the permanent accommodation needs of St. Patrick's National School, Celbridge Community School and St. Raphael's Special School on a campus type arrangement. Work is progressing and is ongoing in respect of technical matters on the acquisition.

It is a priority for my Department to commence the architectural planning process for this site at the earliest possible stage. For the time being, given the commercially sensitive nature of site acquisitions in general, I am unable to elaborate further.