Tuesday, 23 July 2019

Ceisteanna (2093)

Marc MacSharry

Ceist:

2093. Deputy Marc MacSharry asked the Minister for Agriculture, Food and the Marine the status of capital projects within the remit of his Department; the amount spent on each project to date; and the anticipated completion date. [34194/19]

Amharc ar fhreagra

Freagraí scríofa (Ceist ar Agriculture)

The information requested by the Deputy is set out in the following table.

2017

Capital Projects

Amount Spent To Date

Status/Anticipated Completion Date

Haulbowline Island Remediation Project*

€4,099,317

See below

2018

Capital Projects

Amount Spent To Date

Status/Anticipated Completion Date

Haulbowline Island Remediation Project*

€9,701,046

See below

Dredging Works at An Daingean FHC

€5,218,307

Completed December 2018

Landing Pier Dolphins and Fendering Killybegs FHC

€2,122,141

Completed December 2018

Smooth Point Enabling Works Killybegs FHC

€4,609,453

Completed December 2018

Dinish Wharf Extension Castletownbere FHC

€11,399,629

February 2020

2019

Capital Projects

Amount Spent To Date

Status/Anticipated Completion Date

Haulbowline Island Remediation Project*

€576,903

August 2019

Smooth Point Pier Extension, Killybegs F.H.C (tender action stage/ contract not yet awarded)

0

December 2020

* Figures on the Haulbowline Island Remediation Project reflect all expenditure by DAFM on the project including costs reimbursed to Cork County Council in its role as the Minister’s Agent.