Ceist:511. Deputy Sean Sherlock asked the Minister for Education and Skills the status of a project for a school (details supplied) in County Kildare. [33079/19]
Amharc ar fhreagraDáil Éireann Debate, Tuesday - 23 July 2019
511. Deputy Sean Sherlock asked the Minister for Education and Skills the status of a project for a school (details supplied) in County Kildare. [33079/19]
Amharc ar fhreagraThe major building project for this school is at an advanced stage of architectural planning, Stage 2b – Detailed Design, which includes the applications for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents. All statutory approvals have been obtained.
Following a legal challenge, authorisation to re-commence the pre-qualification process issued to the Design Team and school. This advert has closed and the Design Team is currently in the process of compiling a shortlist of contractors for tender stage.
When the pre-qualification process for the main contract and reserved specialists contracts is complete, the project will then be progressed to tender stage.
A tender stage normally takes between 7 and 8 months to complete.