The building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.
This project is one of the school building projects on my Department’s ADAPT 2 (Accelerated Delivery of Architectural Planning & Tendering) Programme. My Department has appointed a Project Manager for the ADAPT 2 Programme, which currently contains 18 school building projects.
The appointment of a Design Team (Architect, Quantity Surveyor, Civil & Structural Engineer, Mechanical & Electrical Engineer and Project Supervisor for the Design Process) for the school in question has been completed.
The Design Team is currently working on Stage 1 of Architectural Planning which includes Site Report, Site Suitability and producing Initial Sketch Schemes. The Stage 1 Presentation to the Department has been scheduled for mid-June.