695. Deputy Matt Shanahan asked the Minister for Defence if he will provide all disbursements of capital spending above €20 million on completed projects for each year since 2016 by name of project, department or body responsible for delivering project, county, NUTS 3 region, type of investment, construction commencement, completion year and actual cost in tabular form. [34187/20]

Amharc ar fhreagra

Freagraí scríofa

The table below outlines the Defence Capital Expenditure Projects in excess of €20 million that have been completed since 1 January 2016.

Name of Project

Commenced

Completed

Actual Cost (VAT incl.)

Naval Service Vessel Replacement Programme & Armament Project

2010

2019

€288 million

Air Corps Fixed Wing Utility Aircraft Project*

2017

2020

€43 million

*Final payments due at end-2020.

Capital expenditure costs for the Army, Air Corps and Naval Service are not identified geographically, but are included in the overall programme costs in the appropriate subheads of the Vote. Under the National Development Plan, as part of Project Ireland 2040, the Defence Vote was allocated €541 million in capital funding for the period from 2018 to 2022.

This level of capital funding allows the Defence Forces to undertake a programme of sustained equipment replacement and infrastructure development as outlined in the White Paper on Defence.