117. Deputy Paul McAuliffe asked the Minister for Education the status of the stage 1-2a application by a school (details supplied); and if she will make a statement on the matter. [39115/20]

Amharc ar fhreagra

Freagraí scríofa

I am pleased to inform the Deputy that funding was approved under the Additional Accommodation Scheme 2016 to enable the school in question to build two general classrooms, one Science Lab with prep area, and one Construction room. In 2019 further approval for nine standard WCs, one WC for assisted users & 1 Socialisation Area was granted.

This project has been devolved for delivery to the school authority and is currently at the Design stage. It is now a matter for the Board of Management to advance this project in that context.