Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects

Dáil Éireann Debate, Wednesday - 13 January 2021

Wednesday, 13 January 2021

Ceisteanna (545)

Bernard Durkan

Ceist:

545. Deputy Bernard J. Durkan asked the Minister for Education the progress to date or in hand in meeting the school place requirements, replacement of facilities, new school requirements and special needs provision in respect of each school project at primary and post-primary levels in Maynooth, County Kildare; the extent to which each project is on target in line with projections notwithstanding the imprecise previous reply in this regard; and if she will make a statement on the matter. [1904/21]

Amharc ar fhreagra

Freagraí scríofa

The following school building projects are being progressed in Maynooth, Co. Kildare to meet expected demand in the area.

Major building projects included as part of the Capital Programme:

Maynooth Post Primary School (R/N 70700A) and Maynooth Community College (R/N 76193Q)

- A building projects to deliver 1,000 pupils places and 2-classroom SEN bases of both of these schools was practically completed in December 2020 and are ready for occupation. However, there are outstanding additional works to take place to complete a shared PE Hall facility.

Gaelscoil Ruairí (RN 20527F)      

- School opened in September 2019 and is currently accommodated in interim accommodation. The proposed new 8-classroom school building plus 2-classroom SEN is at planning permission stage.  A request for further information was received on 18/12/2020.  Until such time as planning permission has been secured, it is not possible to provide a timeline for progression of the project to tender and construction stages.

Maynooth Boys School (RN 17341U) 

- This project commenced construction in December 2020 for a new 24 classroom school and a 2 classroom SEN Base. The construction project is progressing satisfactorily on site and the contract duration is 18 months.

- Maynooth Educate Together (RN 20292E) 

- This project is currently on site and due for completion in Quarter 2 2021. Phase 1 was handed over in 2019, the project when complete will provide for a 16 classroom school plus SEN classes.

In addition the following Additional School Accommodation project has been approved: 

Presentation Girls NS (RN 00779U)

- This project is at the design stage. The project is to provide 3 mainstream classrooms (including allowing for conversion of existing classrooms to provide SEN provision), 2 SET rooms and ancillary accommodation.

As previously advised details of all school building projects both at primary and post-primary level are available on my Department website www.education.ie and this information is updated on a regular basis.

Barr
Roinn