I propose to take Questions Nos. 254, 256, 257, 260, 286, 287 and 293 together.
The Government announced that additional public health restrictions would apply under Level 5 of the Plan for Living with COVID-19 on 6 January 2021. The additional restrictions required all construction activity to cease from 6pm on Friday 8 January, with a number of exceptions. These measures are set out in Health Act 1947 (Section 31A - Temporary Restrictions) (Covid-19) (No. 10) (Amendment) (No. 2) Regulations 2021 (S.I. No. 29 of 2021).
With regard to private housing development, the Regulations provide that housing and construction works ongoing on 8 January can continue where the works required to render the property capable of occupation are scheduled for completion by 31 January 2021.
On 26 January, the Government announced that the current level 5 restrictions will remain until 5 March 2021. Accordingly, no extension has been provided beyond 31 January in respect of private housing development. These restrictions on construction will remain in place until 5 March.