Dáil Éireann Debate, Thursday - 4 February 2021

Thursday, 4 February 2021

Ceisteanna (112)

Seán Sherlock

Ceist:

112. Deputy Sean Sherlock asked the Minister for Education the status of temporary accommodation at a school (details supplied). [6172/21]

Amharc ar fhreagra

Freagraí scríofa

Cork ETB has a project manager in place to provide interim accommodation to meet the schools needs pending delivery of its permanent building.

The planned interim accommodation project was due to be delivered in three phases but phases two and three will now be combined.

- Phase 1 consisted of 2 main-classrooms, 1 SNU, ancillary accommodation and an assembly area. This was handed over to the school on 14 December 2020.

- Phase 2 & 3 combined will consist of 8 main-classrooms, Science Room, Engineering Room and ancillary. It is anticipated that this will start on site in early April 2021 and the expected completion date will be the end of July 2021. 