Schools Building Projects

Dáil Éireann Debate, Wednesday - 24 February 2021

Wednesday, 24 February 2021

Ceisteanna (457)

Cormac Devlin

Ceist:

457. Deputy Cormac Devlin asked the Minister for Education the progress of a school building project (details supplied); and if she will make a statement on the matter. [10020/21]

Amharc ar fhreagra

Freagraí scríofa

I wish to advise the Deputy that It is intended that the school in question will relocate to an existing building currently occupied on an interim basis by another school while awaiting the construction of a building project for that school.

In this regard, the building project for that school is at an advanced stage of the tender process and the Department is currently awaiting a Tender Report from the Design Team which is due in shortly.

Subject to no issues arising during the balance of the tender process it is it is anticipated that the project should commence on site in Quarter 2 of 2021.