Dáil Éireann Debate, Wednesday - 24 February 2021

Wednesday, 24 February 2021

Ceisteanna (69)

Eoghan Murphy

Ceist:

69. Deputy Eoghan Murphy asked the Minister for the Environment, Climate and Communications the way in which decisions are made regarding the order of areas to be connected in the rural broadband plan; and if this list is reviewed on an ongoing basis. [10421/21]

Amharc ar fhreagra

Freagraí scríofa

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools.

The network rollout is divided into 227 Deployment Areas (DAs) across the country. These are typically an area of approximately 25km in radius and in total they cover 96% of Ireland’s landmass. The architecture of the network design is specifically based on the design of the NBI network coming from the eir exchanges or the metropolitan area networks (MANs) managed by Enet. It is based on an engineering design that allows NBI to get to every premises as quickly as possible working within the confines of how fibre networks are built. Each DA creates a ‘fibre ring’ which is essential to ensure reliability, robustness and resilience. Critical to the success of the network, NBI’s fibre rings are built with back-ups, ensuring that in the event of one fibre cable being disrupted, the whole network continues to perform. Each fibre ring that NBI deploys is designed in a way that is non-discriminatory meaning that as the rollout progresses, it may pass relatively urban areas at the same time as passing some of the most remote premises within the intervention area. The design will utilise existing infrastructure to a very significant degree.

The deployment plan forecasts construction commenced in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.

The NBI website provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. I am advised that NBI is working to provide more detail on its website, with a rolling update on network build plans. NBI also has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.