Schools Building Projects

Dáil Éireann Debate, Wednesday - 28 April 2021

Wednesday, 28 April 2021

Ceisteanna (606)

Matt Carthy

Ceist:

606. Deputy Matt Carthy asked the Minister for Education when funding will be allocated to a school (details supplied) in respect of its application for necessary additional accommodation works; the timeframe within which she expects these works to be completed; and if she will make a statement on the matter. [22109/21]

Amharc ar fhreagra

Freagraí scríofa

I can confirm to the Deputy that this school was granted approval and funding to build two mainstream classrooms and an Assisted-User WC under the Additional Accommodation Scheme for 2020. The delivery of this project is devolved to the school authority.

My Department's officials recently reviewed the school's Stage 2B submission and I am pleased to confirm that this project has now been approved to proceed to tender stage; the school has been informed of this positive development.  It is too early at this stage in the process to give a timeline for delivery.

Barr
Roinn