The Defence Forces Built Infrastructural Programme 2020-2025 was published in January 2020. This Programme, which is a 5 year plan, provides a blueprint for investment in the Defence Forces built infrastructure over a multi annual timeframe
The following capital projects are included in the Infrastructure Development Plan for progression in respect of the locations referenced by the Deputy:
Dundalk Aikens Barracks - Central Heating Boiler Decentralisation-Tenders in respect of this project are currently under evaluation and a Main Contractor is expected to be appointed in the coming months; Dining Hall Upgrade- planned for commencement in 2024 for completion in 2025.
Gormanstown Camp - Upgrade to NDA Range- Contractor is currently on site with works expected to be completed later his year; Dining Hall Upgrade- planned for commencement in 2024 for completion in 2025.