159. Deputy Sean Sherlock asked the Minister for Education further to Parliamentary Question Nos. 830 and 831 of 15 June 2021, the name of the schools in bundle of design and build projects; and the listed priority given to each school in tabular form. [33941/21]

Amharc ar fhreagra

Freagraí scríofa

On June 14th 2021, a total of 10 projects were tendered to the Design and Build Contractors Framework and are listed below in tabular form.

Roll Number

School Name

 76333G

Carrigtwohill Community School, Carrigtwohill, Co Cork

 20442U

Scoil Chliodhna Community National School, Carrigtwohill, Co Cork

 18000W

Scoil Mhuire Naofa, Carrigtwohill, Co Cork 

 20017F

Scoil an Spioraid Naoimh, Laytown, Co Meath

 20546J

Ashbourne Community National School, Ashbourne Co. Meath

 62330U

Patrician Academy, Mallow, Co Cork

 68346T

Belmayne Educate Together Secondary School, Belmayne, Dublin

 20519G

Stapolin Educate Together National School, Belmayne, Dublin

 68241F

Stepaside   Educate Together Secondary School, Dublin

 68309N

Limerick Educate Together Secondary School, Limerick

As the individual contracts will be awarded to different contractors it would not be possible at this time to identify individual projects as priorities across the above listing. The tender process means that all projects will be tendered under the same timeframe with receipt of all ten tenders on the same date.

Once individual Contractors are appointed the priority in each case will be to ensure that the schools are constructed in the shortest possible timeframe consistent with achieving the highest quality buildings in accordance with design and contractual requirements. As Contractors are appointed, the Department will keep each school informed of the construction programme underpinning the contract.

That being said, as Carrigtwohill is a campus and will be awarded to a single Contractor, the Department has identified the Community College as requiring priority in the construction programme for that campus.