Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Broadband Infrastructure

Dáil Éireann Debate, Thursday - 18 November 2021

Thursday, 18 November 2021

Ceisteanna (145)

Claire Kerrane

Ceist:

145. Deputy Claire Kerrane asked the Minister for the Environment, Climate and Communications when a premises (details supplied) will be connected by National Broadband Ireland; the reason the date for the completion has moved from 2021 to 2025; the reason for this delay; and if he will make a statement on the matter. [56700/21]

Amharc ar fhreagra

Freagraí scríofa

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 554,000 premises, including almost 100,000 businesses and farms along with some 699 schools.  I am advised by NBI that, as of 5 November, almost 274,000 premises across all counties have been surveyed or have surveys underway and over 125,000 premises have build underway. NBI has also advised that the first premises are connected in Cavan, Cork, Galway, Limerick and Monaghan and over 30,000 premises are available to order and pre-order across 12 counties. 

In addition to the challenges to the delivery of the NBP due to the Covid-19 pandemic, NBI has faced a range of other challenges due to the sheer scale and complexity of rolling out fibre to the home in a rural environment. These include significant tree trimming to ensure cable can be placed on overhead poles, remediation of ducting that has been in place for many decades, the co-ordination of hundreds of contracting crews and addressing the many issues arising week on week which could not have been foreseen until the build crews commenced work on the ground. The Department has worked closely with NBI to put in place a remedial plan under the Contract. This plan addresses delays experienced by NBI, primarily arising as a result of the Covid-19 pandemic, and re-baselines milestones for 2021. Work is underway to re-baseline milestones for 2022 and beyond. This has resulted in some changes to timeframes for connection for end-users.  

Given the scale and complexity of delivery of the new high speed broadband network under the NBP, I am advised that any dates provided by NBI on its website are based on the best available information at the time and may be subject to change. NBI has recently published details of its full deployment schedule on its website, www.nbi.ie , which enables all premises within the intervention area to have an anticipated service activation date range.

The network rollout for the National Broadband Plan is divided into 227 Deployment Areas (DAs) across the country.  These are typically an area of approximately 25km in radius and in total they cover 96% of Ireland’s landmass. Counties are generally made up of a number of DAs which means there are differing timescales for connection across county areas. My officials raised the specific issue referred to in the Question with NBI who confirmed that the associated date for anticipated service activation was published for the first time in September 2021 and no other date(s) had previously been published for this premises. There are nearby Deployment Areas in Ballinasloe and Galway City with different activation dates but this premises does not fall within these Deployment Areas.

I appreciate people's frustration when they are living so close to a fibre network but cannot get a connection to that network in the immediate term, particularly given the heightened importance of connectivity during the Covid-19 pandemic. The NBP will ensure that in all such cases a future proofed high speed broadband network will be built to serve these premises and work to deliver on this is underway. 

Barr
Roinn