490. Deputy Richard Boyd Barrett asked the Minister for Education if she will provide a report on the online patronage process system that was opened in 2018 to decide 42 new schools to include name of school and catchment area, type of patronage of each school; if enrolment has opened on the schools; if the schools have temporary sites or permanent sites or both identified; the stage the building of these schools is at; when they are expected to be completed; and if she will make a statement on the matter. [4855/22]

Amharc ar fhreagra

Freagraí scríofa

I wish to advise the Deputy that the information requested relating to the 42 new schools, announced in 2018, is set out in tabular format for ease of reference.  

When a new school is being established to cater for demographic need a patronage process is run. This patronage process is open to all patron bodies and prospective patrons. Parental preferences for each patron, from parents of children who reside in the school planning areas concerned, together with the extent of diversity currently available in these areas, are key to decisions in relation to the outcome of this process.

The Online Patronage Process System (OPPS) has been developed by the Department to provide objective information to all parents and guardians which will allow them to make an informed choice in expressing a preference for their preferred model of patronage for their child’s education.

The patronage process for new schools is overseen by an external independent advisory group, the New Schools Establishment Group (NSEG). Following their consideration of the Department’s assessment reports, the NSEG will submit a report with recommendations to the Minister for consideration and final decision. The assessment reports and the NSEG recommendations for all such patronage processes are available on the Department's website (www.education.ie ) and gov.ie.

All school building projects are progressed through the preliminary and detailed design stages aligning to my Department's Design Team Procedures prior to proceeding to tender and construction. These stages ensure that all projects are designed against the twin benchmarks of quality and cost control. Under these procedures my Department engages with the Project Manger to ensure that high standards in respect of both benchmarks are met. My Department constantly endeavours to progress projects through the stages of architectural planning, tender and construction in the shortest timeframes possible consistent with ensuring high quality and cost effective design.

As with all school building projects, pre planning meetings are required with the Local Authority in advance of preparing a Planning Application. This is to ensure the highest probability of a successful planning application in the shortest time possible. A considerable amount of work is required following the pre-planning meeting to prepare a suitably detailed application. The Department must await a decision on planning from the local authority. A notification to grant planning can be received after 8 weeks, although there is a possibility for the Local Authority to request further information (RFI). There is always also the possibility of an An Bord Pleanala Appeal (ABP) and if this occurs it may add a further six to eight months or more to the final planning decision date.  If planning is delayed, the Department has to put contingency arrangements in place to support the operation of schools.  

It is not therefore, possible to provide an indicative timeframe for the progression of projects to tender, construction and completion stages until such time as the necessary statutory approvals have been secured.

Post Primary

-

Announced 

for 

School Planning Area 

School Name 

Roll Number

establishment 

Established 

Patron 

Permanent Site Status

Building Project

Donaghmede_Howth_D13/Belmayne/Clongriffin 

Belmayne ETSS 

68346T

2019

2019

Educate Together 

Acquired

Stage 3

GalwayCity & Oranmore (Regional Solution) 

Galway ETSS 

68347V

2019

2019

Educate Together 

Negotiations

Site Acquisition Process

Laytown & Drogheda (Regional Solution) 

Drogheda ETSS 

68348A

2019

2019

Educate Together 

Agreement in principle 

Stage 1

Wicklow 

Wicklow ETSS 

68345R

2019

2019

Educate Together 

Negotiations

Site Acquisition Process

Blanchardstown_West D15 & BlanchardstownVge_D15 (Regional Solution) 

Ériu Community College 

76574F

2020

2020

Dublin and Dún Laoghaire Education and Training Board (DDLETB) 

Negotiations

Site Acquisition Process

Goatstown_Stillorgan DLR 

Goatstown Educate Together Secondary School

68366C

2020

2020

Educate Together 

Acquired

Stage 2a

Enfield (Kilcock school planning area) 

Enfield Community College 

76595N

2020

2020

Louth and Meath Education and Training Board (LMETB) 

Acquired

Stage 2b

Citywest/Saggart (Tallaght & Newcastle_Rathcoole school planning areas) (Regional Solution) 

Coláiste Pobail Fóla 

76594L

2020

2020

Dublin and Dún Laoghaire Education and Training Board (DDLETB) 

ETB Property

Stage 2b

Dublin6_Clonskeagh & Dublin_6W (Regional Solution) 

Harold’s Cross Educate Together Secondary School 

68365A

2020

2020

Educate Together 

Acquired

Stage 2b

Ballincollig 

Le Cheile Secondary School Ballincollig 

68385G

2021

2021

Le Chéile Schools Trust 

Negotiations

Site Acquisition Process

Booterstown_Blackrock & Dunlaoghaire (Regional Solution) 

Booterstown Blackrock and Dunlaoghaire Educate Together Secondary School 

68387K

2021

2021

Educate Together 

Acquired

Stage 2b

Donaghmede_Howth_D13/Baldoyle/Stapolin 

Patron to confirm 

N/A

2021

Deferred 

TBD 

Negotiations

Site Acquisition Process

Dublin2_Dublin4 

Patron to confirm 

N/A

2021

Deferred 

TBD 

Acquired

Project Brief

Kilcoole & Greystones (Regional Solution) 

Greystones Community College 

76596P

2021

2020

Kildare and Wicklow Education and Training Board (KWETB) 

Agreement in principle 

Stage 1

Sallynoggin_Killiney_DLR/Cherrywood 

Patron to confirm 

N/A

2021

Deferred 

TBD 

Acquired

Stage 2b

Drumcondra_Marino_Dublin1 

Patron to confirm 

N/A

2022

Deferred 

TBD 

Negotiations

Project Brief

Building Project

Site Acquisition - site may be acquired by the Department or by the school's patron

Project Brief stage - this includes determining the project brief and schedule of accommodation

Stage 1 - Preliminary

Stage 2 - Design (which is divided into Stage 2a - Developed Sketch Scheme and Stage 2b - Detailed Design)

Stage 3 - Tender Action, Evaluation and Award

Stage 4 - Construction

* Pre-designated as an Irish-medium school

Primary

No. 

School Planning Area 

School Name 

Roll Number

Announced  for establishment 

Established 

Patron 

Permanent Site Status

Building Project

1

Booterstown_Blackrock 

Gaelscóil Laighean 

20518E

2019

2019

An Foras Pátrúnachta 

Agreement in principle with Local Authority executive, subject to approval by Elected Members 

Site Acquisition Process

2

Donaghmede_Howth_D13 

Stapolin ETNS 

20519G

2019

2019

Educate Together 

Acquired

Stage 3

3

Drumcondra_Marino_Dublin1 

Gaelscóil Áine 

20517C

2019

2019

An Foras Pátrúnachta 

Negotiations

Site Acquisition Process

4

Dublin6_Clonskeagh & Dublin_6W (Regional Solution) 

Harolds Cross ETNS 

20520O

2019

2019

Educate Together 

Acquired

Stage 2b

5

Dunshaughlin 

Dunshaughlin Community National School 

20521Q

2019

2020

Louth & Meath Education & Training Board 

Acquired

Stage 2b

6

Glasheen_CorkCity/Pouladuff 

South Lee ETNS 

20522S

2019

2019

Educate Together 

Agreement in principle with Local Authority executive, subject to approval by Elected Members 

Site Acquisition Process

7

Goatstown_Stillorgan_DLR 

Goatstown Stillorgan ETNS 

20523U

2019

2019

Educate Together 

Acquired

Stage 2a

8

Kilcoole/Newtownmountkennedy 

Newtownmountkennedy ETNS 

20524W

2019

2019

Educate Together 

Acquired

Stage 1

9

Killester_Raheny_Clontarf 

KRC ETNS 

20525B

2019

2019

Educate Together 

Negotiations

Site Acquisition Process

10

Leixlip 

Leixlip ETNS 

20526D

2019

2019

Educate Together 

Negotiations

Site Acquisition Process

11

Maynooth 

Gaelscóil Ruairí 

20527F

2019

2019

An Foras Pátrúnachta 

ETB Property

Stage 2b

12

Swords/South 

Rivervalley Community National School 

20528H

2019

2019

Dublin & Dun Laoghaire ETB 

Negotiations

Site Acquisition Process

13

Swords/North 

Broadmeadow CNS 

20529J

2019

2020

Dublin & Dun Laoghaire ETB 

Minister Property

Pre Stage 1

14

Carrigaline 

Owenabue Educate Together National School 

20534C

2020

2020

Educate Together 

Negotiations

Project Brief

15

Donabate 

Gaelscoil na Mara* 

20530R

2020

2020

An Foras Pátrúnachta 

Approval in Principle

Site Acquisition Process

16

Newcastle_Rathcoole/Saggart 

Rathcoole Educate Together National School 

20549P

2020

2020

Educate Together 

ETB Property

Stage 2a

17

Sallynoggin_Killiney_DLR/Cherrywood 

Cherrywood Educate Together National School 

20535E

2020

2020

Educate Together 

Acquired

Stage 4 (expected completion July 2022)

18

Bray/Woodbrook Shanganagh 

Patron to confirm 

20536G

2021

Deferred 

TBD 

Negotiations

Site Acquisition Process

19

Clondalkin_D22 

Patron to confirm 

20537I

2021

Deferred 

TBD 

Minister Property

Project Brief

20

Donaghmede_Howth_D13 

Gaelscoil Ghráinne Mhaol* 

20538K

2021

2021

An Forus Patrunachta 

Minister Property

Stage 1

21

Dublin2_Dublin4 

Gaelscoil Eoin* 

20539M

2021

2021

An Forus Patrunachta 

Minister Leased Property

Stage 1

22

Gurranbraher_CorkCity 

Patron to confirm 

20540U

2021

Deferred 

TBD 

Agreement in principle 

Site Acquisition Process

23

Kilkenny/City, Western Environs 

Patron to confirm 

20541W

2021

Deferred 

TBD 

Aquired

Site Acquisition Process

24

Naas 

Patron to confirm 

20542B

2021

Deferred 

TBD 

Negotiations

Site Acquisition Process

25

Sallynoggin_Killiney_DLR/North 

Sallynoggin ETNS 

20543D

2021

Deferred 

Educate Together 

Agreement in principle 

Stage 1

26

 

 

Sallynoggin_Killiney_DLR/Cherrywood 

Patron to confirm* 

20544F

2022

Deferred 

TBD 

Negotiations

Site Acquisition Process

Building Project

Site Acquisition - site may be acquired by the Department or by the school's patron

Project Brief stage - this includes determining the project brief and schedule of accommodation

Stage 1 - Preliminary

Stage 2 - Design (which is divided into Stage 2a - Developed Sketch Scheme and Stage 2b - Detailed Design)

Stage 3 - Tender Action, Evaluation and Award

Stage 4 - Construction