295. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage the up-to-date position with regard to a development (details supplied) in south County Kildare; when it is expected to open; and if he will make a statement on the matter. [17484/22]

Amharc ar fhreagra

Freagraí scríofa

The project that the Question refers to is a significant initiative which will support communities, and create exciting opportunities for recreation and ways to experience interesting places from new perspectives.

Waterways Ireland obtained planning permission for the Project, a 46 kilometre stretch from Lowtown to Athy, including the canal side works and the roadside works. Work commenced on site in the late summer of 2020 with completion of works by Waterways Ireland expected in late 2022.

To date, Waterways Ireland has completed 20.2km of the canal side works, which equates to 55% of the towpath to be developed. A further 5.6km are nearing completion and in Q2 2022 it is scheduled to commence the section from Athy to Milltown Bridge in south County Kildare.

Kildare County Council is the Project Manager for the Project and is responsible for overall project delivery. Project updates are published regularly by Kildare County Council on its website.