222. Deputy Pat Buckley asked the Minister for Education if a successful contractor has been appointed to a school (details supplied); if so, when work will commence; the expected finishing date for same; and if she will make a statement on the matter. [21570/22]

Amharc ar fhreagra

Freagraí scríofa

The Letter of Intent (LOI) issued on the 15th of February 2022 to the preferred tenderer.  This allows the preferred bidder to put in place the Bond, Insurances and confirmations of all legal arrangements required under the Contract.  

Following receipt of all the necessary documentation, the Department will be in a position to issue the Letter of Acceptance (LOA), which will allow the contractor to mobilise on site. 

My Department will advise the Board of Management when the Letter of Acceptance issues.