Dáil Éireann Debate, Tuesday - 31 May 2022

Tuesday, 31 May 2022

Ceisteanna (116)

Mark Ward

Ceist:

116. Deputy Mark Ward asked the Minister for Transport when Kishogue train station will open to the public; the cost of this; the reason for the delay; and if he will make a statement on the matter. [27289/22]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy may be aware, the National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area including, in consultation with Iarnród Éireann (IÉ), Kishogue station. 

I am informed by the NTA that extensive work is needed by IÉ before Kishogue Station can be brought into use, including meeting present day accessibility and systems requirements which are above and beyond the original requirements. 

The investment will total circa €3.8 million and it is anticipated that the station will become operational for the public in 2023.